Katy ISD officials are making progress on projects from its November 2023 bond, where voters authorized the use of $806.56 million for new schools, facility upgrades and safety projects.

In a nutshell

At the April 22 board meeting, trustees approved budgets and construction contracts for 12 projects, which will begin construction through 2027.

However, district officials said in an email that the final contract amounts have not been set.

The details


At the meeting, contractors were approved for the following projects. The project scope is from KISD’s bond website, while the estimated cost and timeline are from the approved contract. Officials have not confirmed the project scope correspond with their respective contract.

Mayde Creek Elementary School renovations
  • Location: 2698 Greenhouse Road, Houston
  • Type: Mechanical, electrical and plumbing renovations; roof; architectural improvements to provide spaces for curriculum and programs
  • Contractor: Anslow Bryant Construction LTD
  • Timeline: spring 2027-August 2028
  • Estimated cost: $18.45 million
Beck Junior High School renovations
  • Location: 5200 S. Fry Road, Katy
  • Type: Mechanical, electrical and plumbing renovations; 10 classroom building additions
  • Contractor: Anslow Bryant Construction LTD
  • Timeline: spring 2026-August 2027
  • Estimated cost: $31.5 million
Sundown Elementary School renovations
  • Location: 20100 Saums Road, Katy
  • Type: Mechanical, electrical and plumbing renovations; roof; architectural improvements to provide spaces for curriculum and programs
  • Contractor: Anslow Bryant Construction LTD
  • Timeline: spring 2027-August 2028
  • Estimated cost: $20.7 million
Hayes Elementary School renovations
  • Location: 21203 Park Timbers Lane, Katy
  • Type: Renovations
  • Contractor: Stewart Builders LLC
  • Timeline: August 2025-August 2027
  • Estimated cost: $19.5 million
McRoberts Elementary School renovations
  • Location: 3535 N. Fry Road, Katy
  • Type: Renovations
  • Contractor: Stewart Builders LLC
  • Timeline: August 2025-August 2027
  • Estimated cost: $18.3 million
Maintenance and Operations facilities and East, South and West Transportation
  • Location: 20380 Franz Road, Katy
  • Type: Provide for office space, exterior open space and parking
  • Contractor: The Whitining-Turner Contracting Co.
  • Timeline: TBD-August 2027
  • Estimated cost: $6 million
What else?

In addition to these projects, trustees also approved contracts for other lower-cost projects such as expanding the Mary L. Hopkins Law Enforcement Center and chiller replacements at the Miller Career & Technology Center and Taylor High School.