Trustee Rebecca Fox said that in addition to the new buildings—including Junior High No. 19 in the new Grange development aimed at alleviating the capacity challenges in the northwest quadrant—she “appreciated” the upkeep of existing buildings that “breathe new energy and excitement” into the campus.
“We don't just need a new school because there's growth,” she said at the Oct. 21 meeting. “We need to take care of our existing buildings that we've already invested in and make sure that all children feel valued in and that we keep up to date with the needs of our students' population.”
The details
At the Oct. 27 meeting, trustees approved contractors for several projects, including:
Construction of Junior High No. 19
The campus, located on Schilpf Road, will have 10 additional classrooms and accommodate 1,600 students.
- Contractor: JLA Construction Services LLC
 - Timeline: summer 2026-June 2028
 - Estimated cost: $60.5 million
 
The elementary school, located at 21800 Westheimer Parkway, will see new windows and exterior sealants as well as a new multilayered roofing system for the 115,000-square-foot building.
- Contractor: Atlas Universal Inc.
 - Timeline: early 2026-summer 2026
 - Estimated cost: $2.64 million
 
The elementary school, located at 22605 Provincial Blvd., will receive new windows and exterior sealants as well as a new multilayered roofing system for the 89,000-square-foot school.
- Contractor: Reliable Commercial Roofing Services Inc
 - Timeline: early 2026-summer 2026
 - Estimated cost: $1.92 million
 
Initially approved in April, McRoberts and Hayes elementary schools' renovation contracts required amendments and preliminary budgets to allow the contractor, Stewart Builders, to buy long-lead materials and finalize costs. Those steps were required to keep design development on track to begin construction in November, said Lisa Kassman, executive director for facilities, planning and construction.
McRoberts Elementary School renovation
The renovation for McRoberts Elementary, located at 3535 N. Fry Road, will include refreshed interiors, site access and entry layout enhancements, new library and music space layouts, modernized classrooms and restrooms, as well as a dedicated special education wing to reduce the number of portable classrooms.
- Contractor: Stewart Builders
 - Timeline: November 2025-late 2026
 - Estimated cost: Added $5.5 million to $18.3 million
 
The renovations at Hayes Elementary, located at 21203 Park Timbers Lane, will bring HVAC repairs, site access and entry layout enhancements as well as the relocation of the library, music rooms and special education spaces.
- Contractor: Stewart Builders
 - Timeline: November 2025-late 2026
 - Estimated cost: Added $4.5 million to $19.5 million
 

Moving forward
The board requested a potential closed session review of safety protocols given the amount of glass used in the renovated buildings, trustee Dawn Champagne said.
			
									
											