Upcoming projects
FM 1461 expansion
Project: FM 1461 is being expanded in Prosper from a two-lane rural road to a six-lane urban road.
Update: The project is currently in the design phase. The Texas Department of Transportation has revised its schedule on this project, requiring utility relocations by August 2027.
- Timeline: Q1 2027-Q1 2030
- Cost: $45.2 million
- Funding source: Texas Department of Transportation
FM 428 expansion
Project: FM 428 is being expanded in Celina to a six-lane divided roadway from Dallas Parkway to Preston Road.
Update: The project is currently in the design phase which is anticipated to be completed in 2026.
- Timeline: 2026-TBD
- Cost: TBD
- Funding Source: city of Celina
Project: Four new lanes are being designed for Frontier Parkway in Celina, which will run from FM 1385 to Dallas Parkway. The project will also include bridges, drainage, signs and lights.
Update: The project is currently in the design phase.
- Timeline: TBD
- Cost: $6.2 million
- Funding sources: city of Celina
Project: TxDOT has designed traffic signals for installation in Celina at FM 1385 and Crutchfield Road, FM 1385 and FM 428, and Preston Road and Legacy Drive.
Update: Design of the signals was completed in April 2024 but a timeline hasn’t been set for their installation.
- Timeline: Q1 2024-TBD
- Cost: $100,000
- Funding source: city of Celina
FM 1385 reconstruction
Project: FM 1385 is being reconstructed from US 380 to FM 455 to be wider in Prosper. The existing road is a two-lane rural highway.
Update: The project is currently in the design phase and crews hope to begin construction work by summer 2026.
- Timeline: Q2 2026-Q2 2029
- Cost: $189 million
- Funding source: Texas Department of Transportation
Project: US 380 in Prosper is being widened from four lanes to six lanes. This project runs from the Collin County and Denton County line to Loop 288. Crews will also construct overpasses at Legacy Drive, Teel Parkway and FM 423/Gee Road.
Update: The project is currently under construction, and its timeline has been extended.
- Timeline: Q4 2021-Q1 2026
- Cost: $175.6 million
- Funding source: Texas Department of Transportation
Project: Coleman Street will be widened from a two-lane rural roadway to a four-lane divided roadway between Gorgeous Road and Prosper Trail.
Update: The project is still in the design phase and construction is expected to be in winter of 2025 or 2026.
- Timeline: Q4 2025-Q4 2027
- Cost: $6.65 million
- Funding source: town of Prosper
Project: Crews in Celina are installing permanent traffic signals at Dallas North Tollway and Punk Carter Parkway, and Dallas North Tollway and Light Farms Way.
Update: Design of the project was completed in February and construction began in May.
- Timeline: Q1 2025-Q1 2026
- Cost: $3.5 million
- Funding source: city of Celina
Project: County Road 52 in Celina is being repaved from FM 428 to Outer Loop.
Update: Design of the project was completed in August 2024 and construction kicked off in October that year.
- Timeline: Q4 2024-Q4 2025
- Cost: $2.8 million
- Funding source: city of Celina
Project: Asphalt is being replaced on both County Road 100 and Coit Road. County Road 100 will see asphalt replacement from Preston to Coit. Additionally, asphalt is being replaced on Coit Road from County Road 92 to County Road 134.
Update: Design of the project was completed in June 2024. Construction began in August 2024.
- Timeline: Q2 2024-Q4 2025
- Cost: $3.5 million
- Funding source: city of Celina